Monday, April 7, 2014

House update

There has been a lot of progress done on our home. On the 24th Mike and I had a meeting with the site foreman to go over the layout of the house and make sure they had all the lights and electrical correct. After that we had four days to put in any low voltage electrical we wanted before they started sheetrocking. Here are some pictures of the progress

March 14th- Plumbing and electric are going in


March 18th- Windows!


March 20th- We have a roof!


 March 31st- They start sheetrocking!


April 1st- Getting ready to work on the outside



April 4th- Sheetrock and brick work done.
Brick in front is finished

Main floor family room/dining area

Basement bedroom

Basement bathroom

Basement family room

Under stairs secret hideout

Stair landing where we'll have a bench and bookcases

Upstairs loft/craft area (my sewing area) :)

Sarah's bedroom

Master bedroom

Master Bathroom

April 6th- Wall texturing done.
Family room

Media center/Kitchen

Downstairs bedroom

I love how fast it's moving now. It's looking like they'll be able to finish early which is great news.